Installation of cement raw material air conveying chute:
1. Generally speaking, the inlet and outlet of linear conveying and installation should be inclined downward by 6-10 degrees, and the connection between the upper and lower grooves of the air chute and each groove should be well sealed (padded);
2. A 90 degree bend (divided into left and right) requires turning.;